ANDHRA PRADESH POWER GENERATION CORPORATION LIMITED
VIDYUT SOUDHA  ::  Vijayawada - 520004
Daywise Generation Particulars as on  :  14-12-2019
Station Unit Capacity Daywise generation in MU 1st to 14th Dec 1st Apr to 14th Dec
(MW) 12-12-19 13-12-19 14-12-19 Gen (MU) PLF (%) Gen (MU) PLF (%)
Thermal Power Stations                
Dr.Narla Tatarao Unit 1 210.0 3.78 3.77 3.80 12.92 18.31 753.60 57.95
(Vijayawada) Unit 2 210.0 3.79 3.75 3.71 46.07 65.29 890.02 68.45
  Unit 3 210.0 3.89 3.83 3.79 53.44 75.74 883.66 67.96
  Unit 4 210.0 3.84 3.86 3.78 53.08 75.23 953.43 73.32
  Unit 5 210.0       3.32 4.71 955.70 73.50
  Unit 6 210.0 4.10 4.01 3.94 55.80 79.08 990.66 76.19
  Unit 7 500.0 8.20 8.06 8.08 112.88 67.19 2263.19 73.10
  Station 1760.0 27.60 27.28 27.10 337.51 57.07 7690.26 70.57
Rayalaseema Unit 1 210.0       3.21 4.55 737.38 56.71
  Unit 2 210.0       2.26 3.20 479.05 36.84
  Unit 3 210.0           856.70 65.88
  Unit 4 210.0           776.88 59.75
  Unit 5 210.0           566.03 43.53
  Unit 6 600.0 8.75 8.80 8.76 120.78 59.91 1597.99 43.01
  Station 1650.0 8.75 8.80 8.76 126.25 22.77 5013.81 49.07
APGENCO Thermal 3410.0 36.35 36.08 35.86 463.76 40.48 12704.07 60.17
Hydro Power Stations                
Machkund (AP Utilisation) 84.0 0.80 0.91 0.93 11.79   238.33  
Tungabhadra (AP Utilisation) 57.6 0.64 0.48 0.47 7.37   96.20  
Upper Sileru 240.0 1.57 1.26 1.39 22.19   422.58  
Donkarayi 25.0       0.02   42.27  
Lower Sileru 460.0 2.24 3.39 2.58 34.38   537.07  
Srisailam Right 770.0 0.20 0.24 0.11 2.77   1114.10  
NS Right Canal 90.0       7.27   102.12  
NS Tail Pond Dam   50.0 0.06   0.07 0.87   77.76  
Penna Ahobilam 20.0       0.12   0.52  
Chettipeta Mini Hydro 1.0           1.14  
APGENCO Hydro 1797.6 5.50 6.29 5.55 86.79   2632.08  
 Solar pant at polavaram 5.4 0.02 0.01 0.02 0.28 15.60 5.40 16.06
Solar plant at Talaricheruvu 400.0 1.74 1.46 1.46 13.64 10.15 470.98 19.02
APGENCO Solar 405.4 1.76 1.47 1.49 13.92 10.22 476.37 18.98
APGENCO Total 5613.0 43.61 43.84 42.90 564.47   15812.52  
                   
Machkund (Total) 120.0 1.73 1.73 1.73 24.12   466.17  
Tungabhadra (Total) 72.0 0.64 0.63 0.62 9.37   128.26  
APPDCL                  
SDSTPS unit 1 800.0              
  unit2 800.0              
Total SDSTPS station 1600.0 12.58 11.51 11.18 172.48 32.08 5215.01 52.64
Outage of Thermal Units
Dr NTTPS 5 (210 MW) is under annual Overhaul  from 21:40 on 01.12.19
RTPP 1 (210 MW) is under Reserve Standby from 12:00 on 04.12.19
RTPP 2 (210 MW) is under Reserve  Standby from 04:00 on 05.12.19
RTPP 3 (210 MW) is under Reserve  Standby from 10:14 on 23.11.19
RTPP 4 (210 MW) is under Reserve  Standby from 06:00 on 28.11.19
RTPP 5 (210 MW) is under Reserve  Standby from 23:18 on 23.11.19
Outage of Hydro Units
Machkund 2 (17 MW) is under outage from 09:00 on 10.09.19
Machkund 4 (23 MW) is under outage from 00:40 on 23.11.19 
Outage of SDSTPS Units
SDSTPS 1 (800 MW) is under annual Overhaul from 00:32 on 15.11.19