| Projects under Execution |
| Name of the Project | Capacity (MW) | Estimated Cost (Rs.in Crores) | Funding Agency | Programme of Commissioning |
| Rayalaseema Thermal Power Project, Stage-II | 420 (2 x 210 ) | 1640.00 | PFC | Unit-III : Comisioned on 24.01.2007
Unit-IV : April, 2007
|
| Vijayawada Thermal Power Station, Stage-IV | 500 (1 x 500) | 1950.00 | REC | July, 2008 |
| Kakatiya Thermal Power Project | 500 (1 x 500) | 2150.00 | REC | December, 2008 |
| Krishnapatnam Thermal Power Station | 1600 (2 x 800) | 8432.00 | KFW / PFC | Unit-I : November, 2010
Unit-II :May, 2011
|
| Priyadarshini Jurala Hydro Electric Project (Joint project with Government of Karnataka) | 234 (6 x 39) | 547.00 | PFC | Unit-I : March, 2007
Balance 5 Units at 4 months interval thereafter
|
| Nagarjunasagar Tail Pond Dam Power House | 50 (2 x 25) | 464.73 | PFC | Unit I : July, 2008
Unit II : November, 2008
|
| Pochampad HES Unit IV | 9 (1 x 9) | 20.00 | PFC | September, 2008
|
| KTPS Stage VI | 500 (1 x 500 ) | 2164.00 | PFC | December 2009
|
| Gas Based Power Station at Karimnagar | 2100 (3x700) | 5520 | PFC/REC | Unit I : September, 2009
Unit II : December 2009
Unit III : March 2010
|
| Lower Jurala H.E.P | 240 (6x40) | 885 | PFC/REC | Unit-I : November, 2009
Balance 5 Units at 4 months interval thereafter
|
| Kakatiya Thermal Power Plant stage II | 500 | 2050 | PFC/REC | December 2010
|
Total | 6653 | 25822 | |