Performance over the previous years
2008-2009
Total Generation-33502 MU, highest since inception
Achieved high PLFs of Units of Dr.NTTPS(Vijayawada)
Unit 4:98.73%
Unit 6:98.41%
2006-07
Unit 3 (210 MW) of Vijayawada Thermal Power Station has established a National Record of continuous service for 441 days from 14.12.2004 to 28.02.2006. It has surpassed the previous record of 405 days achieved by 500 MW unit of NTPC
2004-05
Achieved an all time high Thermal Generation of 23360 MU and all time High PLF of 89.7%
Achieved top position among Utilities in All India PLF rankings.
The top three PLF's achieved by our thermal plants.
KTPS V : 94.5%
RTPP : 91.2%
RTS : 90.6%