KAKATIYA THERMAL POWER PROJECT STAGE -I (1X500 MW)
MONTHLY PROGRESS AS ON 01.09.2010
KTPP Stage-I was synchronized with grid on 31.03.2010 at 06:08 Hrs.
Main Plant Package (BTG Package):
Supplier: M/s BHEL
Supply PO: TM-0745, Dt 04.08.2005 for Rs 964.22 Crores
Erection PO: TM-0746, Dt 04.08.2005 for Rs 101.00 CroresRs 1065.22 CR
Zero date: 09.11.2005
Balance Of Plant including Civil works Package:
Supplier: M/s BGR Energy Systems Limited, Chennai
Supply PO: TM-0769, Dt 18.11.2006 for Rs 458.3431 Crores
Erection PO: TC-0770, Dt 18.11.2006 for Rs 18.3864 CroresRs 694.8622CR
Civil PO: TC-0771, Dt 18.11.2006 for Rs 218.1327 Crores
Zero date: 28.09.2006
Completion Schedule: 29 months from date of LOI for all BOP packages.
Engineering Consultancy Services including site supervision:
Agreement was entered in to with M/s. Desein Pvt Ltd., on 31.01.2006 for providing Engineering Consultancy Services including site supervision and inspection services.
Raw Water Transport Package Details:
Order for material, erection, testing & commissioning of Raw water Intake Pump House, Intermediate Booster Pumping Station & break pressure Tank was placed on M/S. Kirloskar Brothers Ltd, Pune on 05.06.2008. Work almost completed along with taking of raw water pipe line. Raw water is pumped in to the reservoir at KTPP site successfully during October 2009 last week.
Major Milestones Schedule:
Sl.No | Activity | Scheduled | Achieved | Anticipated |
1 | Commencement of supplies | 09.12.2006 | 22.12.2006 | |
2 | Start of Boiler Erection | 09.02.2007 | 21.03.2007 | |
3 | Boiler drum lifting | 09.06.2007 | 26.08.2007 | |
4 | Hydraulic test | 09.05.2008 | 08.05.2008 | |
5 | Start of Turbine Erection | 30.09.2007 | 22.05.2008 | |
6 | Start of Condenser Erection | 30.09.2007 | 17.05.2008 | |
7 | Boiler Light up | 09.11.2008 | 28.01.2010 | |
9 | Synchronization | 09.02.2009 | 31.03.2010 | |
10 | COD | 09.04.2009 | Trial operation carried out for 72 hrs from 20:00 hrs on 03.08.2010 to 20:00hrs on 06.08.2010. |
Major Achievements:
|
Works Progress of B.T.G. Works by M/s BHEL
Status of BOP Works Progress:
RAW WATER SYSTEM
·Erection & Commissioning of CW & ACW pumps are completed.
DM PLANT & PTP
INSTRUMENT & SERVICE AIR SYSTEM
·Service Air and Instrument Air compressor are commissioned and kept in service.
FUEL OIL SYSTEM
·Fuel Oil system along with pump house and all tanks and accessories completed.
COAL HANDLING SYSTEM
·Dust suppression and Extraction system commissioning under progress.
·Stacker Reclaimer commissioning under progress.
·3,13,000 MT of coal stocked at site.
ASH HANDLING SYSTEM
·Bottom ash & fly ash evacuation system kept in service. Troubles in Transport Air Compressors occurred and were attended on top priority and system kept in service.
TRANSFORMER YARD
·All Gen. Transformer limbs, Station Transformers, UTs, UATs and bus ducts completed and connected to 400kv switch yard.
·ST-1&2 commissioned and charged.
400 KV SWITCH YARD
·400 kv switch yard construction completed in all aspects and charged
C&I:
·Commissioning of annunciation system on UCP/ECP under progress.