Rayalaseema Thermal Power Project, Stage - III(1x210 MW) |
RTPP Stage-III (1X210 MW), Unit-5 Status as on 04.12.2010
Ø The unit is synchronized with grid on 29.11.2010, at Hrs.
Ø The unit was coal fired with B & C Mills on 30.11.2010 and unit is loaded up to 62 MW.
Ø The unit stream lining operations are under progress, the unit full load is expected by 10.12.2010.