KAKATIYA TPP Stage-II (1x500 MW)
¨ Land and water are available.
¨ Coal block has been allocated by Ministry of Coal at Tadicherla Mines of M/s.Singareni Collieries Company Ltd.
¨ Tenders for Mine Operator Cum Developer is under process.
¨ It is proposed to finalise the Mine Developer Cum Operator by June, 2008 and Coal Production would commence by June, 2010.
¨ It is programmed to start the zero date of the Unit by March, 2008.
¨ Unit would be commissioned by March, 2011.